Monroe Street 1 – Indiana Ave to Chelan Ave

SCOPE OF WORK:  This project consists of the construction of approximately 8200 cubic yards of excavation and embankment, 2300 linear feet of ductile iron water main, 46 drainage

structures, 6000 square yards of sidewalk, 13,000 square yards of 9-inch thick HMA pavement, illumination system, landscaping and sundry utility adjustments, and other

related miscellaneous items.

UDBE's please send in the Underutilized Disadvantaged Business Enterprise (UDBE) Written Confirmation Document with your Proposal. Don't forget to sign it.

You can find the form on this web site under Bid Documents. If you have any questions, please call Kim at 208-683-2646